NPCF Week 14 (4/1-4/7)

  • Tower switched multiple time over the weekend, received complaints from Cray team.
  • Assisted  Blue Waters senior design team on their project.
  • At the request of Cray personnels investigated  causes of chilled water spikes and low flows (strainers issues) 
  • Switched all XDPs chilled water strainers to standby ones and F&S are cleaning all the ones that  were in service.

 

NPCF Week 13 (3/25-3/31)

  • Added AHU 2 on line
  • Planing mForge cage procurement 
  • Planing for cage physical security requirement 

NPCF Week 12 (3/18-324)

  • Water treatment sample was sent to NALCO for the tower and heating loop weekly analysis .
  • New Naclo  water treatment controller was ordered.
  • F&S-Fabricating rack blanking panel.
  • Cooling Tower testing for higher temperature:
    •  Increase the tower control temperature from 50 to 52
    • Added the forth chilled water pumps to reduce pumps power
    • The result was not favorable, as the the temperature  of the chilled water increased the demand by the XDP for flow increased so much the pumps could not maintain the required differential pressure.
    • Reversed the changes to the origenal setting of 50 deg supply chilled water temp
    • Change the towers control point to 45 (50-5) to increase towers utilization and to reduce the import of chilled water from campus, this worked well.

 

NPCF Week 11 (3/11-3/17)

  • Two hard drives failed on the security system (DVR-B)
  • Continued to measure cold aisle temperature in the i/m fiorge.
    • Air supply temperatures is between 50 to 70 depending on the location and mixing with hot air.
    • Temperature at the top of rack around 74 degree.
  • Need to fill all racks empty spaces with blanking panels.
  • Also considering a cold aisle containment for I/m forge aisle.