Work Completed
- Arrived in Champaign on Monday at 2pm, met with KISTI, presented KNSG tutorial, eAIRS, and hosted seminars on Tuesday and Wednesday
- Worked on KISTI Project. There was a new feature request that came out of the meeting and a software bug
- KNSG-100, allow users to create input files from within eAIRS application. This is nearly finished, the interface just needs to be tweaked.
- KNSG-101, for eAIRS, the mesh does not vary in the parameterized runs, only the input file. This is nearly fixed and just needs to be debugged.
Work Planned
- Travel to Champaign Monday to meet with KISIT representatives (Dr. Nam and Dr. Moon) over the next 2 days (Tuesday/Wednesday)
- Work on KISTI Project, continue wrapup
Comments
This week went as planned. Next week will be the final week on the first phase of the KISTI project, I will be finalizing the code and documentation.