Number | Project Title | Group | Requestor | POC | Project Scope | Start Date | End Date | Cost | Status/Progress |
---|---|---|---|---|---|---|---|---|---|
01 | Cooling Tower (1,2) Sump Valves | F&S | MO/Tedra | MO | Repairs and rebuild the failed valves | 07/2018 | Waiting for the end the of cooling season(May-Jun) to start work | ||
02 | Site instrument caliberation | F&S | MO/Tedra | MO | Annual calibration of controls instruments, pressure, temperature and positioners | 06//2018 | Waiting for the end the of cooling season(May-Jun) to start work | ||
03 | UPS inspection | TBD | MO/Tedra | MO | Review current PM and modify to meet OEM minimum requirement | 04/2018 | |||
04 | Cooling tower controller Replacement | Facilities | MO | MO | Replace the defective controller | 03/2108 | 9,000.00 | Process started, getting pricing and approval | |
05 | Create water treatment program | Facilities | MO | MO | Establish water treatment program to protect the integrity of cooling and heating systems | 03/2018 | In progress | ||
06 | mForge cage | Facilites | MO/Tedra | MO/Tedra | Build cage around mForge racks at NPCF | 04/2018 | Started 3/13/18 | ||
07 | i/m Forge | Facilites | MO | MO | Mitigate cold aisle air mixing (build cold aisle containment) | 03/2018 | collecting aisle air temperature data | ||
08 | PUE-Server room 2020 temperature increase | Facilities | MO/Tedra | MO | Work with all NPCF stakeholder to gradually increase room temperature up 77 Deg F | 01/2018 | In-progress, pending finishing iforge air flow management. | ||
09 | Chilled water pumps sequence of operation | F&S | MO | MO | Modify pumps controls sequence to reduce power consumption and reduce pressure spikes | 06/2018 | Waiting for the end the of cooling season(May-Jun) to start work | ||
10 | Condensing water pumps sequence of operation | F&S | MO | MO | Modify pumps controls sequence to reduce power consumption | 07/2018 | Waiting for the end the of cooling season(May-Jun) to start work | ||
11 | Cooling tower fans sequence of operation | F&S | MO | MO | Modify fans controls sequence to reduce power consumption | 08/2018 | Waiting for the end the of cooling season(May-Jun) to start work | ||
12 | Site orgnaiztion | Facilities | MO/Tedra | MO/Tedra | Implement 5S system for NPCF and NCSA | 12/2017 | On going. | ||
13
| Towers blowdown | F&S | MO/Tedra | MO/Tedra | Relocate the meter and the blowdown valve | 5/2018 | Tower operation dependent | ||
14 | Towers control panel/power | F&S | MO/Tedra | MO/Tedra | Provide dedicated power breaker for each panel | 6/2018 | Tower operation dependent |