Work Completed
- MAEviz
- On Monday we solved the issue of the Synergy special iteration case and then between the rest of Monday and Tuesday I tested the solution, added an example of using a style to color an analysis output, and documented parts of the code that would help the Synergy developers complete their tasks for the Hungarian exercise.
- Resolved an issue with MAEviz launching under 64 bit windows. The Eclipse 64 bit launcher was not included in the product file.
- KISTI
- Discussed briefly with Jong about getting started on the KISTI project and what lies ahead. We will setup a meeting to discuss design strategies for the upcoming project.
- Cyberintegrator
- Started cleaning up undesirable UI contributions from Eclipse plugins. I provided some screenshots to Rob to ensure that I was on the right track for what he wanted cleaned up as part of CBI-118. I haven't checked in the code yet since I didn't have write privileges to SVN.
Work Planned
- KISTI
- If contract is completed, begin project to create a Web application version of eAIRs.
- MAEviz
- Assist Synergy visitors with issue running a special iteration case
- Document new analyses created for Synergy visitors
- Cyberintegrator
- Work on cleaning up undesireable UI contributions from Eclipse plugins
Comments
This week went as planned. Next week I will continue working on Cyberintegrator and KISTI.