Work Completed

  • KISTI Project
    1. After the meeting in Champaign, we've determined that the semantic capabilities will be a phase II feature. We came away with a basic project plan for Phase I deliverable to KISTI (an improved, RCP version of PTPFlow that they could install as an application) and Phase II would start moving towards the usage of Beans.
    2. Created an updated Mockup of the KISTI RCP Application based on information from the meeting. I also updated the wiki with some text around the new mockup.
    3. Started working on adding some PTPFlow views to the RCP application. I talked with Al about updating the actions to use the Eclipse commands framework, a more declarative way of adding actions and menus. I will start converting a few of the PTPFlow menus and actions to the commands framework so that Al, Jong and/or myself can later update more of the PTPFlow actions to use the commands framework.
    4. Still working on getting my parameterized workflow to run successfully, it's a simple "echo" message workflow that should echo a message 4 times, but it fails. At this point we're not sure if it's the fact that my machine is behind a router with no real IP address or not. The single run workflow works. Al can run it successfully, Jong did not get a chance before leaving and will try to get it working with Al when he returns. I will continue to work on the RCP application in the meantime.

Work Planned

  • Meeting in Champaign to discuss how to integrate semantic features into the KISTI project.
  • Work on KISTI Project

Comments

I travelled to Champaign on Monday May 24 and I took a personal day on Friday May 28.