StartEndWhat System/Service is affectedWhat is happening?What will be affected?Contact PersonStatus
2019-06-04 09002019-06-04 1700ISDA VM's including NCSA open sourceUpgrade of the storage server hosting the VM data, as well as upgrades to VM serversAll of ISDA VM's will be down during this time, including NCSA Open Source
2019-06-23 07002019-06-23 1400LSSTPower maintenance in NPCF
  • lsst-dev01, lsst-xfer, lsst-dbb-gw
  • Slurm verification cluster
  • PDAC/Kubernetes/LSP clusters
lsst-admin@ncsa.illinois.edu

Status
colourBlue
titlescheduled

2019-06-23 06:002019-06-23 20:00

Facility power and cooling/ all production area will be impacted


Commissioning new protective relays: 30 minute rolling power outage

Sonexion re-power: 12 hours work duration 

Expect down time of 2 hours minimum for all production areas

Blue waters down time between 10-12 hours

rantissi@illinois.edu

...