StartEndWhat System/Service is affectedWhat is happening?What will be affected?Contact Person
01/12/2019 8AM01/12/2019
1PM
BW/Mainframe resourceHung threads on scratch/home, paused the scheduler, HSN requires full reboot to recover 9:30AMMainframe will rebooted and all running jobs are lost. HSN locked up requiring a reboot to recoverTimothy Bouvet

2019-01-16

10:00

2019-01-16

11:00

NPCF facility fire safety/power and coolingEnergizing the emergency power off panel (EPO)

We don't expect it to affect production but the EPO can trip all power circuits and CRAH units.

rantissi@illinois.edu
2019-01-23
9:00 
2019-01-23
5:00 
netdot.ncsa.illinois.edupatches and migrationnetdot.ncsa.illinois.eduhelp+neteng@ncsa.illinois.edu
2019-01-10 08:002019-01-10 12:00LSST

Monthly maintenance

  • Power rebalancing in NPCF L73
  • Switch maintenance in NPCF M73, N73, P73

primarily:

  • lsp-stable
  • lsp-int
  • Oracle

secondarily:

  • VMs (dbb-gw VM will be migrated to another host temporarily)
  • admin testing services
lsst-admin@ncsa.illinois.edu
2019-02-05 07:002019-02-05 19:00iForge/cForge/SIMPL/aForgeQuarterly MaintenanceAll systems will be unavailable during the maintenance.iforge-admin@ncsa.illinois.edu

...