NPCF Week (7/1-7/7)

  • No incident to report
  • F&S continues  PM work
  • F&S Installing new weather station and tower fans vibration switches
  • reduction in leak alarms after the insulation repairs
  • Loading docs cleaning 

NPCF Week(6/17-6/23)

  • F&S started  VFDs annual preventive maintenance, it will take a week or so to complete, this is will not impact critical equipment but will impact office and mechanical rooms ventilation. 
  • brought in an outside mechanical contractor to estimate the cost to preform boilers tune up to verify combustion safeties and boiler setting. 

...