NPCF Week (7/1-7/7)
- No incident to report
- F&S continues PM work
- F&S Installing new weather station and tower fans vibration switches
- reduction in leak alarms after the insulation repairs
- Loading docs cleaning
NPCF Week(6/17-6/23)
- F&S started VFDs annual preventive maintenance, it will take a week or so to complete, this is will not impact critical equipment but will impact office and mechanical rooms ventilation.
- brought in an outside mechanical contractor to estimate the cost to preform boilers tune up to verify combustion safeties and boiler setting.
...