NPCF Week 17 (4/22-4/28)

  • Tower is cycling more more Towers are cyclingmore often of/off due to weather warming up.
  • Sealed data center floor tile penetration to minimized air leakage, CRAH fans speed dropped from 100% to 75% saving energy
  • Floor cleanedGeneral building cleaning.
  • New tower controller is working well.
  • Submitted new facility PM in CMMS.
  • Tedra will be working with WireCrafter to order the cage.  

...