Fall 2020 runs Aug 25th - Dec 9th
Training Schedule (week 1- week2) Sessions in Green are all new NCSA staff invited
Day & Rooms/Zoom | Tuesday (25th) TBA | Wednesday (26th) TBA | Thursday (27th) TBA | Friday (28th) TBA | Monday (31th) TBA |
---|---|---|---|---|---|
0900 | Pre-eval (Dr. Rosu) | ||||
1000 | Program Overview | Desktop Support | Composable Systems | ||
1045 | Break | Break | Break | Break | Break |
1100 | Neteng Matthew Kollross | Software Directorate Jong Lee | ISL Overview | ||
1200 | Lunch | Lunch | Lunch | Lunch | Lunch |
1300 | NCSA Communications | IRST group | IRST - Technical | ||
1400 | Project Manager Overview | Core group | Core - Technical - need to confirm this one | ||
1445 | break | break | break | break | break |
1500 | Neteng Matthew Kollross | ||||
1600 |
One-Day embeds (tentative)
21st (Wed) | 22nd (Thurs) | 23rd (Fri) | 24th (Mon) | 25th (Tues) | |
---|---|---|---|---|---|
Student 1 | |||||
Student 2 | |||||
Student 3 | |||||
Student 4 | |||||
Student 5 |
Fall 2020 Group Assignments:
- Student 1 -
- Documentation page
- Student 2 -
- Documentation page
- Student 3 -
- Documentation page
- Student 4 -
- Documentation page
- Student 5-
- Documentation page
Overall Schedule: Aug 25th through Dec 9th
Week # | Week starts | Activities |
---|---|---|
0 | Aug 24th | 4 days intro & training |
1 | Aug 31st | 1 days training 4 days embedded- each day varies the intern + group |
3 | Sep 7th | Sep 7th Labor day Holiday (excused) 1 day embedded+ group selections Wed start of designated group internship |
4 | Sep 14th | |
5 | Sep 21st | |
6 | Sep 28th | |
7 | Oct 5 | |
8 | Oct 12 | |
9 | Oct 19 | |
10 | Oct 26 | |
11 | Nov 2 | |
12 | Nov 9 | Start of special project for the Group, up to 25% effort |
13 | Nov 16 | |
14 | Nov 23 | Fall Break, this is excused time off |
15 | Nov 30 | |
16 | Dec 7 | Dec 9th last day & equipment turn in, final eval |