Tasks and Schedule
The following tasks define the approximate order in which the development of this project will progress. Following the completion of Task 4 and then after each successive task, a meeting will be scheduled with the stakeholders to demonstrate the use of the web application at that time, to gather feedback about the usability and look and feel of the web application, and to gather requirements and comments about the upcoming tasks.
...
Project duration: The week of 1/310/2010 to the week of 4/411/2010
Task | Name Description | Duration |
---|---|---|
1 | Software Engineering and Administration | 1 week |
2 | Building the Spatial Database | 1 week |
3 | Building the Web Feature Server | 1 week |
4 | Develop Initial Map Component | 4 weeks |
5 | Develop Browsing Capability | 2 weeks |
6 | Develop Attribute View for Entities | 2 weeks |
7 | Develop Table/List View for Search Results | 2 weeks |
8 | Final Deployment of Component | 1 week |
9 | Preparing Transition Proposal |
|
10 | Discussion and Decision on Transition |
|
...