Project duration: The week of 1/310/2010 to the week of 4/411/2010

Task

Description

Duration

1

Software Engineering and Administration

1 week

2

Building the Spatial Database

1 week

3

Building the Web Feature Server

1 week

4

Develop Initial Map Component

4 weeks

5

Develop Browsing Capability

2 weeks

6

Develop Attribute View for Entities

2 weeks

7

Develop Table/List View for Search Results

2 weeks

8

Final Deployment of Component

1 week

9

Preparing Transition Proposal

 

10

Discussion and Decision on Transition

 

...