Current Status
On this page you can find a summary of the completed tasks to date based on the planned tasks and schedule.
All the tasks, issues, bugs can be found at Jira (Issue Tracking System).
=Done |
=Postponed |
=In progress
Task 1: Software Engineering and Administration (Week 1)
Create and configure Jira issue tracking
Create and configure SVN repository
Create and configure Confluence wiki
Setup Development environment and document steps on wiki
Create and configure Hudson continuous build
- Moved to Task 4
Create development mail group
- Need to find who will be in the mailing list
Locate appropriate hardware and configure web server for the application
- The hardware was located and it is being set up
Task 2: Building the Spatial Database (Week 2)
Configure PostGIS database
- Waiting for the hardware to be ready
Obtain and clean Illinois Census Tract Data
Import Illinois Census Tract Data into database
- Wating for the PostGIS DB
Obtain and clean sample business location data
Import into sample business location data into database
- Wating for the PostGIS DB
- Test accuracy of database with imported data
- Test performance of database with imported data
Completed Tasks
Jira Issues | ||||
---|---|---|---|---|
|