NumberProject TitleGroupRequestorPOCProject ScopeStart DateEnd DateCost

Status/Progress

01Cooling Tower (1,2) Sump ValvesF&SMO/TedraMORepairs and rebuild the failed valves07/2018  Waiting for the end the of cooling season(May-Jun) to start work
02Site instrument caliberationF&SMO/TedraMOAnnual calibration of controls instruments, pressure, temperature and positioners   06//2018  Waiting for the end the of cooling season(May-Jun) to start work
03UPS inspectionTBDMO/TedraMOReview current PM and modify to meet OEM minimum requirement04/2018   
04Cooling tower controller ReplacementFacilitiesMOMOReplace the defective controller03/2108 9,000.00Process started, getting pricing and approval
05Create water treatment programFacilitiesMOMOEstablish water treatment program to protect the integrity of cooling and heating systems03/2018  In progress
06mForge cageFacilitesMO/TedraMO/TedraBuild cage around mForge racks at NPCF04/2018  Started 3/13/18
07i/m ForgeFacilitesMOMOMitigate cold aisle air mixing (build cold aisle containment)03/2018  collecting aisle air temperature data
08PUE-Server room 2020 temperature increaseFacilitiesMO/TedraMOWork with all NPCF stakeholder to gradually increase room temperature up 77 Deg F01/2018  In-progress, pending finishing iforge air flow management.
09Chilled water pumps sequence of operationF&SMOMOModify pumps controls sequence to reduce power consumption and reduce pressure spikes06/2018  Waiting for the end the of cooling season(May-Jun) to start work
10Condensing water pumps sequence of operationF&SMOMOModify pumps controls sequence to reduce power consumption 07/2018  Waiting for the end the of cooling season(May-Jun) to start work
11Cooling tower fans sequence of operationF&SMOMOModify fans controls sequence to reduce power consumption 08/2018  Waiting for the end the of cooling season(May-Jun) to start work
12Site orgnaiztionFacilitiesMO/TedraMO/TedraImplement 5S system for NPCF and NCSA12/2017  On going.

13

 

Towers blowdownF&SMO/TedraMO/TedraRelocate the meter and the blowdown valve5/2018  Tower operation dependent
14Towers control panel/powerF&SMO/TedraMO/TedraProvide dedicated power breaker for each panel6/2018  Tower operation dependent