 Sep 5 (Wed) Sep 6 (Thurs)Sep 7 (Fri)Sep 10 (Mon)Sep 11 (Tues)
Pradeep

 Systems

Chit Khin

 IRST

James Eyrich

Jennie

 IRST

James Eyrich

 ISL

Yan Zhan

Systems

Jacob Rundall

 SEAS

 ITS

Douglas Fein

 

Overall Schedule: Aug 28th through Dec 13th

Week #

Week starts

Activities

0

Aug 27th

4 days intro & training (after MLK)

1

Sep 3rd

1 days training

4 days embedded- each day varies the intern + group

3

Sep 10th

1 day embedded+ group selections

Tues start of designated group internship

4

Sep 17th

 

5

Sep 24th

 

6

Oct 1st

 

7

Oct 8th

 

8

Oct 15th

 Oct 10th, Meet and greet with NCSA Industry Partners

9

Oct 22nd

 

10

Oct 29th

 

11

Nov 5th

 
12

Nov 12th

  • continue to work within designated groups
  • special project, expected involvement is up to 25%
13Nov 19th Fall break
14Nov 26th 
15Dec 3rd 

16

Dec 10th

Dec 13th final day

final eval and feedback, equipment turn in

...