Work Completed

  • Worked on second draft of Hurricane ERC proposal with Jong. There will be additional work this weekend to finalize the second draft since it is due on Monday January 18th (a holiday).
  • Reviewed KISTI contract text.
  • Worked on Data Catalog briefly. Most of this week was spent working on proposals.

Work Planned

  • Review KISTI contract
  • Work on second draft of ERC Thrust 4 based on reviewers comments from January 9th meeting.
  • Work on Data Catalog

Comments

This week went as planned. For the week of January 18-22 I will continue working on ERC text if needed and probably getting started with Market Maker.